Overview
Step-by-step
1. Advise in Teams and tap Won in the app
When the customer confirms they want to proceed on HT:- Post in your Teams channel that you are doing HT
- On Solar Progress, tap Won in the header (or mark Won when you finish — follow your team lead’s timing)
2. Office checks documents
The office will check:- Survey
- Design (OpenSolar)
- Documents generated in the app
3. Send HT application screenshot
In Hometree, screenshot the application showing these boxes filled in:- Panel
- Inverter
- Battery
- Generation
4. Office matches and approves
The office compares your screenshot to the contract and survey. When it matches, they approve you to continue with HT in Hometree.5. If passed on HT
Once HT is passed:- Office checks all documents are signed in the app
- You take payment (£500 holding via Lopay, then Mark Payment Complete in the app)
6. Book installation
In the app:- Book Installation — installer, date (2+ weeks out), 09:00 slot
- See Step-by-step guide — Book installation
7. Consolidate
Complete any remaining consolidation steps your team requires (welcome email, final checks).8. Send sale update in Teams
Post the sale update in Teams so everyone knows the job is complete.Contract before Hometree
Generate and sign the EPVS contract in the app first. Use those details to fill the Hometree application — do not complete HT before the contract information is ready. Order in the app:- Solar Projection
- Hometree (open HT — step marks complete)
- Contract Generation → sign contract
- Fill HT using contract details
- Continue payment and installation steps